PREbeton expansion - Successful industrial project alongside smooth plant operation

PREbeton expansion - Successful industrial project alongside smooth plant operation
Published:

The construction of halls and the development of production facilities is a key element of industrial development. The PREbeton production hall extension was a complex project, which was not only outstanding in size, but also in the fact that it was carried out while the factory was in continuous operation. In this blog post, we present the details, challenges and successes of the expansion works, which highlight the most important aspects of professional hall construction.

The challenge: Responding to growing demand

PREbeton's first hall opened in 2020, but the rapid growth in production capacity made it clear by the end of the first half of the year that expansion was needed. The plans prepared by the client team provided precise guidance, which greatly facilitated the preparation and pricing process. At the same time, the biggest challenge of the project was to ensure that the factory's operations were not disrupted by the construction and that the delivery of products remained uninterrupted.

With the new halls and three-storey offices, not only has production capacity increased, but the working environment has also been significantly improved, contributing to more efficient operations.

Execution: precision and efficiency

One of the most important aspects of building the hall was to separate the construction traffic from the day-to-day operations of the factory. This allowed the construction to have minimal impact on production processes. The project sought to involve local businesses, thus strengthening the local economy.

The construction phase started with earthworks and deep foundations in the autumn, followed by the installation of reinforced concrete pillars before Christmas. At the beginning of the new year, work continued at a rapid pace, and the project was ahead of schedule and ahead of schedule. This allowed the foreign technology installers to start trial production on time.

For more details, visit the PREbeton official website.

The handover: on time and without a hitch

The final stage of the project was the technical handover and obtaining the occupancy permit. Carefully prepared documentation and effective cooperation resulted in the occupancy permit being obtained two weeks ahead of schedule. The repair of the defect list was carried out quickly and efficiently, so that the new halls were available for the client on time.

The key to hall building success

This project is an outstanding example of how professional hall construction can combine precision, efficiency and a customer-centric approach. The smooth running of the factory during construction is a clear testimony to the high level of professionalism and commitment of all those involved in the project.

The expansion of PREbeton is a milestone in the life of CPH, not only in size but also in importance. We have proven that our team can successfully tackle the most complex challenges while providing the highest level of service.

Why choose us for hall construction?

Building a hall is not just a technical process, but a comprehensive service that takes into account the specific needs of the client and the project environment, from design to construction. Our aim is to achieve outstanding results in every project, on time and on budget.